St Patricks College, Thurles, Co Tipperary

Project Summary

Scope of Works

Supplied and installed new mains water system, new cold water storage tank, new water services booster pump, new hot water calorifier, hot water return pump, thermostatic mixing valves, showers, installation of system mains, hot and cold pipework, solar panel hot water system, insulated all new pipework and flushed and chlorinated entire water systems.

Protective Services

The Fire Fighting services scope of works for this project includes the following:

  • Supplied and installed of 2kgCO2 and 6kg ABC type fire extinguishers complete with suitable fire point signage and support brackets in locations identified on the drawings
  • Supplied and installed fire blankets as per drawings. Oil Services Installed
  • Extended from existing oil supply to boiler room to connect to the two oil fired boilers
  • Oil supplies to each boiler complete with fire valve assembly and filter

Hot and Cold Water Services Installation

  • Supplied and installed new mains water system as indicated on water drawings
  • Supplied and installed new cold water storage tank as indicated on drawings as specified
  • Supplied and installed new water services booster pump as specified
  • Supplied and installed new hot water calorifier as indicated on drawings and as specified
  • Supplied and installed hot water return pump
  • Supplied and installed thermostatic mixing valve at all WHBs
  • Supplied and installed showers as specified
  • Installed system mains, hot (flow and return), and cold pipework as indicated on drawings
  • Supplied and installed solar panel hot water system complete including twin coil hot water cylinder
  • Supplied and installed thermostatic mixing valves as specified
  • Insulated all new pipework
  • Pressure tested and certified the system
  • Flushed and chlorinated the entire new water services system on completion.

Soils & Wastes Services

  • Supplied and installed new above ground soils and waste pipework from new sanitary ware as indicated on the drawings
  • Supplied and installed new Soil vent stacks and roof vents as indicated on the drawings
  • Supplied and installed fire collars as specified
  • Supplied and installed floor gulley drains as specified on drawings
  • Supplied and installed CWS overflows

Ventilation

The ventilation and Air Conditioning Scope of works for this project included the following

  • Supplied and installed new toilet extract systems including fans, attenuators, grilles, dampers ductwork,controls etc. as specified and indicated on drawings
  • Insulated all new supply air ductwork
  • Supplied and installed fire/smoke dampers as per drawings
  • Supplied and installed duct access hatches as per drawings
  • Supplied and installed and commission ventilation control panel
  • Tested and commissioned all ventilation systems

Heating Services Installation

  • Installed new boilerhouse plant, pipework and ancillaries as per the drawings including:
    • New Oil fired boiler & burner
    • Pipework, valves and headers
    • Pumps
    • Pressurization unit and expansion system
    • Valves, motorized valves and ancillaries
    • Oil pipework and fire valves assemblies
    • New flue systems and draught stabilizers
  • Supplied and installed new LPHW distribution pipework as per drawings
  • Supplied and installed radiators and radiator control valves as specified throughout
  • Tested and commissioned and certified the new system
  • Supplied and installed new heating control panels and field devices and test and commission system
  • The contractor liaised with the client agreed time schedules for heating system and set point temperatures for the system temperature stats

The contract included a full demonstration of the system to the consultant and the client.

Insulation

The Insulation services installation scope of works for this project involves the following:

  • Supplied and installed pipework insulation to new hot & cold water pipework systems
  • Supplied and installed pipework insulation to new LPHW pipework systems
  • Supplied and installed ductwork insulation to new supply Ventilation ductwork systems as required

Project Description

Client: St Patricks College, Thurles
Project Type: Full Mechanical Installation and Services
Contract Price: €487,000.00
Contract Duration: 7 Months
Main Contractor: Monami Construction